About Mugs Award Winners How to Apply

2005 Mugs Stump Award Winners:
Anderson/House—Rupal Face of Nanga Parbat

The Central Pillar of the Rupal Face M5/5.9, WI4 (4,100m)
Sept. 1-8, 2005, Vince Anderson & Steve House

On 6 September, at 17:45 Vince Anderson and I stood on the windless summit of Nanga Parbat after six days of climbing. We had climbed a new, direct route on the Rupal Face. Famous for being one of the biggest, if not the biggest, wall in the world and because it saw its first ascent in 1970 by Reinhold and Gunther Messner.

Vince and I started at 4:00 a.m. on September 1 carrying 16kg of equipment each. We had pared the equipment to the minimum we thought was necessary. We carried a 1kg tent and one synthetic sleeping bag that I sewed especially for this route. We had the minimum of food and fuel. Our rack consisted of 3 cams, 10 nuts, 9 titanium pitons, 5 ice screws, and 10 runners. We climbed on a 8mm rope and carried a 5mm static rope to use for the many rappels back down the face. Each was cut to 50 meters long.

August 31
4 a.m. We left basecamp to start the route. The weather forecast is good for 7 days. At about 6:30 a.m. we arrived at the Bazhin glacier (the start of the face). Numerous snow avalanches were releasing on the face after receiving sun for the first time in many weeks. After watching for a bit, we decided to allow the face to clean itself for a day. We returned to basecamp and the weather was hot, dry, and clear all day.

September 1
4:00 a.m. We again left basecamp, this time for real. Around 6 a.m. we picked up our gear we cached at the glacier and started up the lower slopes of the face. It was much quieter now, it seemed that most of the snow avalanches had run the previous day.

The warmth came on quickly as another hot and dry day was upon us. We worked through some crevasses at the bottom of the face while trying to avoid exposure from the large ice avalanched from the seracs above (the guillotine). After one hour on the glacier we were on a prominent rocky rib that provides safety. We followed the rib for several hundred meters before being forced out left and back into a large couloir. Now avalanches were running frequently down the couloir, but were restricted in their course by a deep channel in the snow. We were able to stay to the side of the channel for a few hundred meters more, then were forced to cross it between sloughs. It only took a few moments to cross, but it proved to be exciting nonetheless as avalanches came rushing down the flume with increasing frequency as the day progressed. Now we continued cramponing up 40-degree snow for several hundred meters more until we had to recross the channels (now there were two of them). We did so quickly, and again were back on the rocky buttress. At the top of the buttress we were at about 5,100 meters and even with the bottom of the next rocky step, which is the crux of the route. We traversed a snow slope to the base of the slope and found a good bivy in the bergschrund there. This is the same bivy site Bruce and Steve used in 2004. It was hot and there was plenty of melt- water running so we could fill up without melting snow on the stove.

September 2
We left the bivy at 3:00 a.m. in the dark to avoid exposure to rockfall. There was ice in the section immediately above the bergschrund that required us to belay several hundred feet where Steve and Bruce had soloed in 2004. By the time we arrived at the crux, it was in full sunlight and rocks were beginning to fall. The pitch consisted of a snow-filled steep corner and the rock was covered with a new glazing of ice. The ice was not thick enough, or solid enough, for screws and often picks would shear through it. Snow covered the underlying rock and made it difficult to dry-tool and find protection. Protection was very inadequate on this pitch and the climbing was tedious. After spending much time climbing and protecting it to half-height Vince needed a break and lowered off a good piece to let Steve finish the pitch.

Steve opted to lead without a pack (and haul). This made things a bit easier for him, but still the protection was scarce and the climbing serious. He dry-tooled a section of loose and slopey rock (5.9). This pitch took us several hours to complete and all the while volleys of stones and ice would periodically rain down upon the belay. After the crux there were several more mostly easy pitches to the top of the rock buttress. We simul-climbed much of this section. It was now 1:00 p.m. and we had been out for 10 hours. We elected to bivy here, as it was safe, despite having gained only 300 meters from the last bivy. This is also the same place Steve and Bruce bivied in 2004 on their second night. Again we reaped the benefit of the warm weather and filled our pot with melt-water.

September 3—The eighteen-hour day
At 5 a.m. we left camp. We ascended a short snow ramp above camp and traversed across an avalanche runnel that ran big several times during the previous night due to serac-avalanches. From here we continued climbing 45-degree snow below another rock buttress and traversed another avalanche runnel. At this point we diverged from the 2004 route. We decided to do that because the 2004 route seemed dangerous due to high snow levels in 2005 and direct pillar is a more aesthetic and difficult line. The excitement of trying a new line that had some serious question marks about it won out.

Several hundred more meters of steep snow brought us to the base of a rock buttress and safety from avalanches. A few moderate mixed pitches got us onto ice runnels above. We did many 150-meter simul-pitches just left of the ridge crest and eventually the day ended. We continued climbing in to the night, now pitch by pitch. We encountered one difficult mixed pitch of snow and steep loose rock. Steve led this pitch and puked at the belay afterwards. From here we could traverse right onto the hanging glacier that is one of the keys to this route. We found a wild, but safe, bivy under a serac. It was 11:00 p.m. and we were both very tired from the effort. We were at approximately 6,200 meters.

September 4—Key Passage
After sleeping in, we left camp around 10:30 a.m. We ascended easy snow slopes above the bivy that eventually yielded to 45-degree snow and ice. The rock headwall above was steep and we needed to find an easy passage through it. A little ways up, we found a nice WI 3 ramp leading through to the left. This was a key section that looked possibly impassable from photos, so it was a relief to find this section of water ice. As we climbed this, the day came to an end and we began looking for a place to bivy. Steve led up snow and ice to the ridge on our left in hopes of finding a good snow to make a tent platform. As he mounted his steed, a large piece of it fell out beneath him. A single tool placement in snow saved him from a huge whipper and large chunks of snow hammered Vince. A bit further on, we found a spot on the ridge that could be leveled to the width of the tent, barely. The ledge was tiny and precarious, so we stayed tied in for the night should the snow underneath cut loose. We were at approximately 7,000 meters.

September 5
Again a 10:30 a.m. start due to the length of the previous days effort. We rapped from our perch back to the snow slopes below. From here, we began heading up easy ice to the upper snow slopes of the ramp system we were on. The altitude effect was obvious here and we were moving slow. We plodded away up these slopes and gained the crest of the ridge just below a short mixed passage leading to the upper snow slopes very near to where Steve and Bruce had turned back the previous year. We were also right above the Merkl Icefield. We made our high camp here at 7,400 meters.

September 6—Summit Day
At 3:30 a.m. we set off for our summit attempt with one light pack between the two of us with 3 liters of water, 2 liters of Spiz (energy mix), several packs of GU each and 50 meters of 5mm cord.

After two pitches of mixed climbing, we began plodding up deep, steep, unconsolidated, faceted snow. This process was extremely slow, difficult, and discouraging. After 100 meters of this, the snow surface had strengthened enough to allow us to travel on top.

We continued up moderately steep snow and ice until we were able to gain a rocky ridge crest to our left. It was slow moving up the easy mixed terrain on the ridge. The weather was superb, it was even slightly hot.

By mid-day, we joined the upper Messner route at around 7,900 meters. We could see faint hints of the Korean climbers' tracks from July. This eventually brought us to easy snow and by 4:00 p.m. we arrived at the false summit. There, at 8,000 meters, Steve took off his boots to dry off his socks in the sun and Vince took a 5-minute nap.

At 5:45 p.m. we arrived at the summit. We savored a few minutes together, took in the marvelous views in all directions, shot some photographs and at 6:00 p.m. descended from the summit. We made it down the easy summit snowfields before darkness caught us. We continued descending our route of ascent, rappelling many sections with our 50 meters of rope until we reached the top of the two mixed pitches above camp where we had another rope. Two rappels from here and a short walk had us both back to camp at 3:00 a.m., 24 hours after starting. We made some water and promptly went to sleep.

September 7
After a light night's sleep we left camp around 8:00 a.m. We began by doing 6 steep rappels down to the Merkl Icefield to join the 1970 Messner route. Upon reaching the Merkl, we found a tent abandoned by the Koreans.

We continued down-climbing the Merkl Icefield and eventually began rappelling. We reached the approximate height of camp 2 (ca. 6,000 m.) by nightfall and continued descending. By 11:00 p.m. we reached what we thought to be the site of camp 1 (ca. 5,500 m.) and bivied under a serac. Steve's headlamp batteries were failing and Vince inadvertently dropped his lamp forcing us to sleep here.

We could see many large bonfires awaiting us below and hear the local villagers drumming in celebration.

September 8
After a coughing-fit filled night, we woke around 7:00 a.m. and continued our slow descent to base camp. Exhausted from 8 days on the go and precious little sleep, we arrived in camp around 2:00 in the afternoon to the great excitement of our Liaison Officer and other locals.

Afterwards:
We have been overwhelmed by the local response to our ascent. All the way out to the road head locals stopped us and congratulated us. In Tarshing (the road head), about 200 schoolchildren turned out to greet us with bouquets of flowers, posters commemorating our climb, and flower leis. The town had a ceremony and the mayor and school headmasters all made speeches. Wild! It turns out the whole valley was watching our progress by seeing our headlamps each night. And the summit day was so clear, many people watched us summit through binoculars.

Summary:
Nanga Parbat. The Central Pillar of the Rupal Face. Sept 1-8, 2005. Anderson/House. (4,100m, M5/5.9, WI4)

A note from Steve and Vince: Note that if you measure the face from the Bazhin Glacier right where the face starts, it is 4,125 meters. Some people measure the face as 5,000 meters, but to get 5,000 meters you have to measure from the village of Tarshing where you start the trek to basecamp. 4,100 meters seems to us like an honest measurement of the amount of climbing on the face.

 

Back to Award Winners

Sponsored by: